Work on sewerage and rainwater basin Heer van Scherpenzeelweg (Mierlo)
Earlier we informed you about work to reduce flooding in the vicinity of the Heer van Scherpenzeelweg. The tender has now been completed. Contractor company vd Boomen BV from Den Dungen is carrying out the work on behalf of the municipality of Geldrop-Mierlo.
Work
Work includes:
- Demolition of existing pavement
- Earthwork and sewerage work
- Construction of a storage basement
- Installation of paving, landscaping and traffic measures
Planning
We have started preparations. Implementation will begin Sept. 29, 2025 (week 40). Completion is scheduled for mid-April 2026, depending on conditions such as weather and possible archaeological discoveries.
The attached sketches show the phasing and implementation periods for 2025. The remaining phases will follow in 2026.
- Orange = phase 1: weeks 40-48
- Yellow = phase 2: week 44-49
- Blue = phase 3: weeks 46-49
- Red = phase 4: weeks 47-51

Reachability and contact
Questions about the accessibility of your premises during the work? If so, please contact:
- Han van Ewijk (contractor company vd Boomen): 06-18477699
- Ad van Rooij (contractor company vd Boomen): 06-22516365
Other questions? Please contact team Realization (Municipality of Geldrop-Mierlo):
- Kevin van Gorp or Bas van Lieshout at (040) 289 38 93.