Skandia multi-purpose building
A multifunctional building is being built in the Skandia neighborhood. The primary school Beneden Beekloop and Dalton Child Center Dommeldal will be housed here. Potje Knor child care will provide child care. And the neighborhood association Hulst-Skandia will also get its own space in the building. The immediate surroundings of the schools will be redesigned.
Want to stay up to date with the latest news? Then sign up for the newsletter schools Skandia.

Temporary housing
In order to build the new multipurpose building, Beneden Beekloop Elementary School moved into the temporary housing, where the neighborhood association also got a temporary place Children's Day Care Potje Knor also placed a temporary unit The demolition of the old building is now in progress and is expected to be completed by the end of 2025.
Temporary construction road
To relieve the neighborhood as much as possible, a temporary construction road has been built for supply and removal of materials and construction equipment. This construction road is located along Beemdstraat and will remain in use until the Dommeldal building is demolished. The contractor will take into account the drop-off and pick-up times of children, so that this also causes as little inconvenience as possible for students and the school. The road is intended exclusively for construction traffic. Parents dropping off children by car can use the temporary parking lot that has been constructed.
New design
We want to design the public space around the school to be safe, green and sustainable. Accessibility, safety and livability have high priority. Therefore, we will realize sufficient parking facilities and the layout around the building will focus mainly on slow traffic.
New play facility
After the multi-purpose building is completed, the Dommeldal building is demolished and the construction road is removed, the actual layout of the public space can begin. In the new situation, this will be next to the intended parking lot. For this we are in discussion with the neighborhood and we ask the neighborhood to help think about the design and layout.
Planning
Completed: Temporary access route ready -
Municipality of Geldrop-Mierlo delivers the temporary access road to the construction site.
Completed: Commencement of groundwork -
Site preparation for placement, foundation work and digging, installation of casing pipes for utilities.
Completed: Placing temporary housing -
May-June 2025 places temporary housing.
Completed: Walk-in evening -
Walk-in evening design Skandia building (location Dommeldal Elementary School).
Completed: Furnish and move Lower Beekloop/Potty Knor to temporary housing -
July-August furnish and move Lower Beekloop/Potty Knor to temporary housing.
Completed: Work asbestos remediation -
Work asbestos remediation inside the school building.
Completed: Start stripping inside -
Start stripping the building on the inside.
Completed: Walk-in evening design outdoor space -
Walk-in evening design outdoor space building Skandia.
Location: Dommeldal elementary school
Currently in progress: Demolition Lower Beekloop -
Start machine demolition of the school building. Work on demolition will be completed by mid-December 2025.
Still to do: Selection and award phase procurement of new construction -
September 2025 - March 2026 selection and award phase procurement of new building.
Still to do: Realization phase new construction -
April 2026 - July 2027 realization phase new construction
Still to do: Furnish and move Lower Beekloop/Potje Knor/Dommeldal to new building -
August 2027 furnish and move Lower Beekloop/Potje Knor/Dommeldal to new building
Still to do: Remove temporary housing/extend construction road with slabs for demolition of Dommeldal building -
Remove temporary housing/extend construction road with slabs for demolition of Dommeldal building.
Still to do: Demolition of Dommel Valley -
October 2027 - January 2028 demolition of Dommel Valley
Still to do: Removal of construction road -
February - March 2028 remove construction road
Still to do: Furnish public space (construct parking lots, furnish outdoor space)
Furnish public space (construct parking lots, furnish outdoor space).
Documents
- Newsletter new Skandia building Oct. 10, 2025
- Newsletter new Skandia building July 18, 2025
- Newsletter new Skandia construction July 1, 2025
- Newsletter new building Skandia - Question and answer information evening May 7
- Newsletter new Skandia building - Question and answer information evening Jan. 23
- Newsletter December 2024