Skandia multi-purpose building

A multifunctional building is being built in the Skandia neighborhood. The primary school Beneden Beekloop and Dalton Child Center Dommeldal will be housed here. Potje Knor child care will provide child care. And the neighborhood association Hulst-Skandia will also get its own space in the building. The immediate surroundings of the schools will be redesigned. 

Want to stay up to date with the latest news? Then sign up for the newsletter schools Skandia.

A drawing of what the new building will look like

Temporary housing

In order to build the new multipurpose building, Beneden Beekloop Elementary School moved into the temporary housing, where the neighborhood association also got a temporary place Children's Day Care Potje Knor also placed a temporary unit The demolition of the old building is now in progress and is expected to be completed by the end of 2025.

Temporary construction road

To relieve the neighborhood as much as possible, a temporary construction road has been built for supply and removal of materials and construction equipment. This construction road is located along Beemdstraat and will remain in use until the Dommeldal building is demolished. The contractor will take into account the drop-off and pick-up times of children, so that this also causes as little inconvenience as possible for students and the school. The road is intended exclusively for construction traffic. Parents dropping off children by car can use the temporary parking lot that has been constructed.

New design 

We want to design the public space around the school to be safe, green and sustainable. Accessibility, safety and livability have high priority. Therefore, we will realize sufficient parking facilities and the layout around the building will focus mainly on slow traffic. 

New play facility 

After the multi-purpose building is completed, the Dommeldal building is demolished and the construction road is removed, the actual layout of the public space can begin. In the new situation, this will be next to the intended parking lot. For this we are in discussion with the neighborhood and we ask the neighborhood to help think about the design and layout.

Planning

Planning work on placement of temporary housing Lower Beekloop.

  1. Completed: Temporary access route ready - Completion date

    Municipality of Geldrop-Mierlo delivers the temporary access road to the construction site.

  2. Completed: Commencement of groundwork - Completion date

    Site preparation for placement, foundation work and digging, installation of casing pipes for utilities.

  3. Completed: Placing temporary housing - Completion date

    May-June 2025 places temporary housing.

  4. Completed: Walk-in evening - Completion date

    Walk-in evening design Skandia building (location Dommeldal Elementary School).

    Results of the meeting on August 26, 2025

  5. Completed: Furnish and move Lower Beekloop/Potty Knor to temporary housing - Completion date

    July-August furnish and move Lower Beekloop/Potty Knor to temporary housing.

  6. Completed: Work asbestos remediation - Completion date

    Work asbestos remediation inside the school building.

  7. Completed: Start stripping inside - Completion date

    Start stripping the building on the inside.

  8. Completed: Walk-in evening design outdoor space - Completion date

    Walk-in evening design outdoor space building Skandia.

    Location: Dommeldal elementary school

    Results of participation in the Skandia School Environment Design

  9. Completed: Demolition Lower Beekloop - Completion date

    Start machine demolition of the school building. Work on demolition will be completed by mid-December 2025.

  10. Completed: Additional design meeting January 26

    Additional design meeting for Skandia neighborhood play and sports area from 7:00 p.m. to 9:00 p.m.

    Location: temporary units, Ziggenstraat 40  

    Report on additional design meeting January 26, 2026

    Presentation of additional design meeting January 26, 2026

  11. Still to do: Selection and award phase procurement of new construction - Completion date

    September 2025 - March 2026 selection and award phase procurement of new building.

  12. Still to do: Realization phase new construction - Completion date

    April 2026 - July 2027 realization phase new construction

  13. Still to do: Furnish and move Lower Beekloop/Potje Knor/Dommeldal to new building - Completion date

    August 2027 furnish and move Lower Beekloop/Potje Knor/Dommeldal to new building

  14. Still to do: Remove temporary housing/extend construction road with slabs for demolition of Dommeldal building - Completion date

    Remove temporary housing/extend construction road with slabs for demolition of Dommeldal building.

  15. Still to do: Demolition of Dommel Valley - Completion date

    October 2027 - January 2028 demolition of Dommel Valley

  16. Still to do: Removal of construction road - Completion date

    February - March 2028 remove construction road

  17. Still to do: Furnish public space (construct parking lots, furnish outdoor space)

    Furnish public space (construct parking lots, furnish outdoor space).