Last works Geldropseweg (Helmond side)

On July 14, the last works of the project for the new bridge (now constructed) over the Eindhovens Kanaal between Mierlo and Helmond will start. Then the installation of the Greenwall Geldropseweg on the Helmond side will be started. The work will be carried out daily between 9 a.m. and 3 p.m. with a half-lane barrier and the deployment of traffic controllers. Fi ets traffic coming from Helmond will be directed to the other side during the entire period of execution.

The traffic measures have been coordinated with the Helmond City Council traffic engineer and it has been agreed that they will put this in Melvin (www.melvin.ndw.nu/public). So please take this adjusted situation into account. Thank you in advance for your understanding. The work will be completed by July 26. The traffic measures will also be removed (or turned off) by then. For questions about this project, please refer to the Municipality of Helmond, Realization and Management: (0492) - 587777, rijksoverheid